A CNC part arrives, the dimensions look right, and the discussion starts anyway. Which material was actually used? Was the part made to the current drawing revision? Where does it say that the critical dimensions were really inspected? These questions can only be answered if the right documents exist. If they are requested after delivery, they cost time, and some can no longer be produced at all.
This article explains, for purchasing, quality assurance and design teams, which quality documents are available for CNC parts, what a material certificate, a first article inspection report and an inspection report each prove, and how to decide what you actually need. The aim is to ask for the documents that suit your part and its application, rather than as many as possible.
Which quality documents are available for CNC parts
Depending on the part and the industry, several documents may be relevant. The overview below lists the most common ones and what they are used for.
| Document | What it proves | Typical use |
|---|---|---|
| Material certificate to EN 10204 | The material and its properties, depending on the type with test results for the delivered batch | Safety-critical and load-bearing parts, material traceability |
| First article inspection report | The sample meets all drawing requirements, tied to a fixed drawing revision | New parts, changes, change of manufacturer, series release |
| Inspection report (measurement report) | Measured actual values of the inspected dimensions | Ongoing production, prototypes with critical dimensions |
| Surface treatment and heat treatment records | A treatment step was carried out as specified | Coated, hardened or otherwise treated parts |
| Manufacturer certification | The company operates a quality management system, for example to ISO 9001 | General minimum requirement for a supplier |
Not every part needs everything. A bracket for a test fixture is fine with an inspection report covering the fit dimensions. A component in a brake or chassis system usually calls for a material certificate and a first article inspection. What matters is what is at stake if the part fails.
Material certificates to EN 10204: 2.1, 2.2, 3.1 and 3.2
EN 10204 classifies inspection documents by what was tested and by who confirms the result. For metal CNC parts you will mainly encounter four types. In the UK the standard is published as BS EN 10204.
- 2.1 declaration of compliance with the order: The manufacturer states that the delivery conforms to the order. It contains no test results.
- 2.2 test report: The manufacturer states conformity with the order and gives results from non-specific inspection, for example samples taken from ongoing production.
- 3.1 inspection certificate: It contains the results of specific inspection on the delivered batch. The inspection department belongs to the manufacturer but is independent of the production department.
- 3.2 inspection certificate: In addition to the manufacturer, an independent external inspection body or an inspector named by the buyer signs it. This is the highest level of independence.
For most industrial applications, the 3.1 certificate is the usual standard, because it gives actual test values for the delivered batch. A 3.2 certificate is mainly requested by customers with special requirements, for example in plant engineering or safety-critical sectors. It lengthens the lead time and costs more, because a third party is involved. Request it only if a standard, your customer or the specification requires it.
It helps to name the type you want explicitly (“material certificate EN 10204 3.1”). A general “material proof required” leaves open whether a declaration of compliance without test values is enough.

Turned and milled metal parts with a flange, bolt pattern and internal thread. Which dimensions and properties need to be documented should be settled before production starts.
Need CNC parts with defined documentation?
Send us your drawing and requirements, and we will agree the inspection scope and documents with the right manufacturing partner before we quote.
The first article inspection report: when you need it
A first article inspection report (FAIR) documents the inspection of samples against the agreed requirements. It links the inspected characteristics, measurement results and deviations to one part and its drawing revision. Unlike an inspection report in ongoing production, it shows that the manufacturing process can deliver the part reliably at the required quality in the first place.
There is no general obligation to provide one, and the scope depends on each customer’s requirements. In the automotive industry, procedures such as production process and product approval under VDA Volume 2 or the AIAG’s PPAP apply. First article inspections are common for:
- a new part,
- changes to design, specification or material,
- new or replaced tooling and fixtures,
- a changed manufacturing process,
- moving production to a different site.
The last point matters particularly for purchasing. If you change supplier or make a part at a second site, a new first article inspection is usually the cleanest way to show equivalence.
A first article inspection report typically contains a cover sheet with the part, revision level, material and drawing, the characteristics with their inspection results grouped by type of inspection (for example dimension, material, hardness or function), the measured values at a suitable precision, the link to the drawing revision, and material proof, often a 3.1 certificate. Where deviations occur, they are recorded with their cause and corrective action. What exactly the report should contain is agreed in advance between buyer and manufacturer, ideally in writing in the purchase order.
Inspection report and inspection scope
The inspection report is the simplest and most frequently requested document. It lists the measured actual values of the agreed inspection dimensions, usually compared with the nominal dimension and tolerance. It shows not only that a part was “OK” but also how much room within the tolerance was left.
The key point is the inspection scope. It defines which dimensions are inspected and on how many parts. Options include inspecting selected, function-critical dimensions or all dimensions on the drawing, in each case on one sample, on a random sample or on every part. The larger the scope, the greater the effort for measurement and documentation, and so the price. A blanket demand for “full inspection” therefore drives up costs without always being necessary.
It has proved useful to mark the inspection dimensions directly on the drawing, for example with numbered positions. This makes it clear to manufacturer and inspector what is to be measured, and the inspection report can be matched to the drawing line by line. All other dimensions are covered by the general tolerance, for example to BS EN 22768-1, and do not have to be recorded individually.
How to request documents correctly
Documents belong in the RFQ, not in the complaint. If you ask for them only after production, you risk extra costs, delays or parts that can no longer be documented, for example if the material was not recorded by batch. These points should be stated in the RFQ and the purchase order:
- Which documents: Material certificate with type (for example EN 10204 3.1), first article inspection report, inspection report, other documents depending on the part.
- Drawing revision: The revision of the drawing to which all documents refer.
- Inspection characteristics and scope: Which dimensions, on how many parts, and with which measuring equipment if that is relevant.
- Timing: When the first article inspection report must be available, before or with the series delivery, and whether the series waits for release.
- Format and assignment: How the documents are matched to parts or batches (for example by order or batch number) and how they are sent.
- Retention: How long the manufacturer should keep the records, if your industry requires it.
The documents should also be itemised in the quotation. This makes clear what is included and what costs extra, and prevents disputes after delivery. For prototypes, a lean inspection report is often enough. Before series release, the full scope is worthwhile. That way you pay for documentation only where it covers a risk.
Documentation for repeat parts and changing manufacturers
For repeat parts and spare parts, documentation becomes a question of comparability. If a part is made over several years in multiple lots or at different sites, the inspection dimensions, drawing revision and document format should stay the same. Only then can results be compared lot by lot and gradual drift be detected.
This is hard to ensure in daily work when several suppliers are used in parallel. Each works with its own templates and terminology, and the documents end up in different inboxes. A single point of contact and one uniform specification for all manufacturers make this easier. You can read more in our articles on contract manufacturing and finding manufacturing suppliers.
Replique makes CNC parts through a network of 450+ certified partners worldwide. You specify the drawing and the documents you need once, and we agree them with the right manufacturing partner. You can find more on our pages for CNC machining on demand and our supplier network.
Want to clarify documentation and inspection scope for your CNC part?
Send us your drawing with your requirements, and we will come back with a quote and suggestions for the inspection scope.
FAQ
Material certificates
What is the difference between a 3.1 and a 3.2 certificate?
Both contain results of specific inspection on the delivered batch. With a 3.1 certificate, an inspection department of the manufacturer that is independent of production confirms the results. With a 3.2 certificate, an external independent inspection body or an inspector named by the buyer also signs.
Do I need a material certificate for every CNC part?
No. For simple parts, fixtures or prototypes, a material specification in the purchase order is often enough. For load-bearing, safety-relevant or regulated parts, a certificate is usual, mostly a 3.1. Your customers’ requirements, standards and specifications decide.
First article inspection and inspection report
What is a first article inspection report, and when do I need one?
A first article inspection report documents the inspection of samples against the agreed requirements and links the results to a drawing revision. It is common for new parts, for changes to design, material or manufacturing process, for new tooling and when production moves to another site. The exact scope depends on the buyer’s requirements.
What does an inspection report contain?
An inspection report lists the measured actual values of the agreed inspection dimensions, usually with nominal dimension, tolerance and result. Buyer and manufacturer agree in advance which dimensions are inspected and on how many parts.
Who decides which dimensions are inspected?
The buyer should specify this, ideally by marking the inspection dimensions on the drawing. All other dimensions are covered by the general tolerance and are not recorded individually.
Costs and ordering
What do certificates and inspection reports cost?
That depends on the scope: the type of certificate, the number of inspection dimensions and inspected parts, and whether an external body is involved. Fixed prices cannot be given without a drawing. Have the documents itemised separately in the quotation.
What happens if the drawing changes?
All documents refer to a specific drawing revision. If design, specification or material change, a new first article inspection is usually due. State the valid revision in every order.